Building 78 Fire Brings $1M Demolition at Alameda Point
The 1942 WAVES barracks on Sunrise Court burned Sept. 17, and the city says it has to come down now.
By The Alameda Pulse

Building 78, a fire-damaged World War II barracks at Alameda Point in Alameda, CA, is being torn down under a city emergency order after a fire on Sept. 17, 2026. The Alameda City Council ratified a $747,500 demolition contract on Oct. 6 and set aside $1 million to cover the whole job.
- Where: 2301 Sunrise Court near Rainbow Court, on the West End at Alameda Point
- When: Fire in the early morning of Sept. 17; demolition contract signed Sept. 22
- Cost: $747,500 for the demolition, $1 million total budgeted
- Who: The city owns it; Silverado Construction is doing the work
- Next: City staff report back at each regular council meeting until the job's done
What happened to Building 78 at Alameda Point?
Building 78 was badly damaged by a fire on Sept. 17, 2026, and the City of Alameda says it can't be saved. The Alameda Fire Department put out a "significant fire" that damaged the entire building. That day, Chief Building Official Oscar Davalos declared it unsafe, ordered it vacated and found it was in "imminent danger of partial or complete collapse."
The order gave the city, which owns the building, 10 days to hire a licensed contractor and 30 days to finish the demolition. City Manager Gerry Beaudin used his emergency powers to sign with Silverado Construction on Sept. 22, skipping the usual bidding process. That's why the council had to ratify the deal afterward.
What was Building 78?
Building 78 was an H-shaped, two-story wood building put up in 1942 as military barracks and used during World War II for the WAVES program, short for Women Accepted for Volunteer Emergency Service. At about 17,724 square feet, it covers roughly a third of a football field.
It wasn't a protected landmark, though. The city says it sits outside the NAS Alameda Historic District, and it was already slated to come down someday. It's inside the footprint of West Midway, the second phase of the RESHAP housing project being built by Catellus and Brookfield.
How much does the Building 78 demolition cost?
The City of Alameda budgeted $1 million for the Building 78 demolition, taken from the Alameda Point Fund rather than the General Fund. Here's where it goes:
- $747,500 for demolition by Silverado
- $70,000 for environmental monitoring by Terraphase Engineering
- $100,000 set aside for surprises
- The rest for fencing, 24-hour security, permits, toxic materials fees and temporary utilities
Only the building itself comes down. Catellus and Brookfield will remove the foundation later as part of their schedule, and the city says it'll sort out the costs with them under their development agreement. Details are in the city's Oct. 6 staff report on the Building 78 demolition.
What happens next?
The Building 78 site is fenced, and part of Sunrise Court is closed until an unstable wall comes down. On Oct. 20, staff told council the contractor was still working and all permits were in hand. Under state rules for emergency contracts, staff will keep asking council to continue the work at every regular meeting until the Chief Building Official signs off. Follow our Alameda Point development news.